Friday , November 24 2017

Will Bengaluru Metro stick to the April deadline?

A reality check of a couple of Metro stations showed they are far from ready yet.

Bangalore-Metro-Station
Pointing out that the trials to test the links will take two months and the inspection by the railways safety commissioner another two or three months, he argues the deadline of April is unlikely to be met.

Bengaluru: Metro’s Phase 1 deadline of April 2017 may be fast approaching but links seem to be progressing slower than the expected.  A reality check of a couple of stations showed they are far from ready yet.

For an instance, at the Chickpet Station, a lot of civil work is still in progress for the underground station. Also, while the Phase-1, which includes 42.3 km of the North South and East West corridors,   connects the Mysore Road to Baiyappanahalli on a Purple line and Nagasandra to Puttenahalli on the Green Line, two sections, the Mantri Square to Kempegowda and Kempegowda to Puttenahalli, have still not been connected.

For more Andhra Pradesh News: Click Here

Though, dismissing all fears, the BMRCL is still hoping to run the trials on lines under Phase I by mid- February as planned. Not willing to buy this, civic activists like Mr. Srinidhi of Praja RAAG remains skeptical.

“At the City Market Station, a lot of earthworks is still being done. Also, there are some prerequisites for trials like energizing a third rail, which carries the power for running the metro and signaling. But you can still see a drilling work and pouring concrete in progress,” he observed.

Pointing out that the trials to test links will take two months and the inspection by the railway’s safety commissioner another two or three months, he argues the deadline of April is unlikely to be met.

“Even if they did perform trial runs with a battery-operated a train, after the safety inspection, there will be faults to rectify and changes to be made, which could take longer,” agrees traffic expert, MN Sreehari.

When contacted, BMRCL Managing Director, Pradeep Kharola however, claimed that the work at Chickpet and KR Market was in full swing.

“The underground portions are ready. Only the outside work is still in process and this will be done by mid- March. Rest assured, BMRCL will stick to its deadline and commuters don’t need to worry,” he said.

Insisting that the underground trial runs would start from mid- February and carry on for around one-and-a-half months, he added, “We cannot tell how long the safety inspection will take, but it is usually fast but not difficult.”

As for the BMRCL receiving a lot of flak for not connecting the Mantri Square Sampige Road line with the Kempegowda station, he said,” The power cables have been installed. The signaling wires are being drawn and the station is almost done.”

Also, most of the third rail, which energizes the metro for the operation, was done on the Green line, leaving only small portions in between, he maintained.

Facebook Comments
Will Bengaluru Metro stick to the April deadline?
5 (100%) 1 vote

About admin

Check Also

salman-khan

Salman Khan, Katrina Kaif’s Swag Se Swagat sets YouTube record

The official Twitter account of YRF Music made the statement about the song from Salman ...